NERC Submits Two Notices of Penalty to FERC


May 4, 2009
On May 4, 2009, NERC submitted the following two NOPs to FERC regarding the violations of Northwestern Energy and Escanaba Municipal Electric Utility (Escanaba). Both NOPs pertain to self-certified violations of Reliability Standard CIP-001-1, R1, R2, R3 and R4, for failure to have a written procedure dealing with possible sabotage events.  NERC did not propose a financial penalty in either NOP.

To view the Northwestern Energy NOP, click here.
To view the Escanaba NOP, click here.