NERC Submits Two Notices of Penalties to FERC

On December 12, 2008, NERC submitted a notice of penalty regarding E.ON U.S. Services Inc.’s failure to complete the SERC-approved Mitigation Plan with respect to its past violation of Reliability Standard EOP-008-0, R1 and its failure to submit a timely notification to SERC regarding completed mitigation of past violations of Reliability Standard FAC-001-0, R1, R2, and R3. 
 
In addition, NERC submitted a notice of penalty regarding Edgecombe Operating Services, LLC’s failure to submit a forecast of expected real power output to assist in operations planning, as requested by the Balancing Authority, each day for the three-day weekend of January 18-20, 2008, in violation of Reliability Standard TOP-002-2, R15. 
 
To view the notice of penalty regarding E.ON U.S. Services Inc., click here. 
To view the notice of penalty regarding Edgecombe Operating Services, LLC, click here.