| Insights | Electric Reliability Blog

Order Granting Rehearing for Further Consideration of March 18, 2010 Order on PRC-023-1

On May 17, 2010 FERC issued an order in Docket No. RM08-13-001, granting rehearing for further consideration on the March 18, 2010 Order approving Reliability Standards PRC-023-1 and direction modification. Reliability Standard PRC-023-1 requires transmission owners, generator owners, and distribution providers to set load-response phase protection relays according to specific criteria in order to ensure that the relays reliability detect and protect the electric network from all fault conditions, but do not operate during non-fault load conditions. To read the order, click here.