NERC Files Reply Comments on WestConnect Utilities’ Request for Extension of Compliance Date for ATC Calculation Reliability Standards

On January 14, 2011, in Docket No. RM08-19, NERC filed reply comments in response to WestConnect Utilities’ (“WestConnect”) request to FERC for an extension of the April 1, 2011 date for compliance with FERC’s order approving Available Transfer Capability calculation Reliability Standards MOD-001, MOD-028-1, MOD-029-1 and MOD-030-2.  NERC believes FERC should dismiss WestConnect’s request and direct it to work with NERC and WECC to develop an appropriate resolution to WestConnect’s concerns.  To view NERC’s reply comments, click here.