FERC Conditionally Accepts NERC Compliance Filing Regarding Rules of Procedure, Pro Forma Delegation Agreements, and MRO / FRCC Delegation Agreements

On October 7, 2011, in Docket Nos. RR10-11, et al., FERC issued an order conditionally accepting  NERC’s Rules of Procedures, NERC’s Pro Forma Delegation Agreement, the Delegation Agreements between NERC and the eight Regional Entities, and the FRCC and MRO Bylaws. The Order conditionally accepted NERC’s February 18, 2011 compliance filing submitted in response to FERC’s October 21, 2010 order. To view FERC’s October 7 order, click here.