FERC Issues Order 759 Approving Transmission Relay Loadability Reliability Standard PRC-023-2

On March 15, 2012, in Docket No. RM11-16, FERC issued Order No. 759 approving both Reliability Standard PRC-023-2 (Transmission Relay Loadability) as well as Section 1700 of the NERC Rules of Procedure, which provide registered entities a means to challenge determinations made by planning coordinators under Reliability Standard PRC-023.  To view FERC’s Order No. 759, click here.