Related Services
FERC Approves Reliability Standards IRO-018-1 and TOP-010-1
- Filter By Electric Reliability Law Blog
On September 22, 2016, in Docket RD16-6-000, FERC issued an order accepting NERC’s May 26, 2016 petition requesting approval of proposed Reliability Standards IRO-018-1 (Reliability Coordinator Real-time Reliability Monitoring and Analysis Capabilities) and TOP-010-1 (Real-time Reliability Monitoring and Analysis Capabilities). Reliability Standards IRO-018-1 and TOP-010-1 require reliability coordinators, transmission operators, and balancing authorities to provide notification to operators of real-time system awareness and monitoring alarm failures. NERC expects the Reliability Standards to improve real-time situational awareness capabilities and enhance reliable operations.
To View FERC’s Order, click here.