| Insights | Electric Reliability Blog

NERC Submits Supplemental Information Concerning July 30, 2010 NOP regarding Kiowa Power Partners

On December 2, 2010, in Docket No. NP10-149, NERC submitted supplemental information regarding Kiowa Power Partners’ (“Kiowa”) commitment to revise its facility ratings methodology within 90 days.  NERC submitted a Settlement Agreement between Texas Reliability Entity, Inc., (“Texas RE”) and Kiowa on July 30, 2010 regarding a violation of Reliability Standard FAC-003-1 Requirement R2.  FERC issued a data and document request on August 27, 2010, directing NERC and Texas RE to submit additional information. On November 8-9, 2010, NERC and Texas RE submitted their response to the data request and a revised Settlement Agreement. To view NERC’s supplemental information, click here.